Summary: The Texas Department of Transportation, TxDOT, is planning to start work in May 2023, scraping and resurfacing I20 from US 180 to the IH20/30 Split. / Willow Park Civics will update and repost this Blog as the project develops.
Latest Update:Thursday, 27 April, 2023
Tags: #Streets
TxDOT I20 Project through Willow Park, starts May 2023
The Texas Department of Transportation, TxDOT, is planning to start work in May 2023 scraping and resurfacing I20 from US 180 to the IH20/30 Split. Project workdays are Sunday thru Thursday, during the evening and night, 7 pm and 6 am.
According to the Willow Park City Engineer Gretchen Vazquez, during the 25 April 2023 Council Meeting, project details are as follows:
CSJ 0008-03-124 IH20 - Parker County, TxDOT
Engineer: TxDOT
Contractor: Northeastern Pavers, LLC
Project is 0% complete
Project consists of milling and overlaying of IH 20 main lanes from US 180 to the IH20/30 Split.
A preconstruction meeting was held on April 13, 2023.
The 256-calendar day construction project will start May 20, 2023.
Project workdays are Sunday thru Thursday, 7pm-6am.
Total contract amount for this project is $18,575,904.96.
Willow Park Civics Research
TxDOT Project Tracker / Search Willow Park
TxDot January 24, 2022 IH 20 CSJ: 0008-03-124, etc Parker County, Texas
TxDOT January 12, 2022, IH 20 CSJ: 0008-03-124, etc Parker County, Texas
Comments