Updates on Crown Road, Kings Gate Road, Ranch House Road, Trinity Drive and tributaries, and Old Fort Road and tributaries. / Willow Park Civics will update and repost as the project develops.
Latest Update: Friday, 28 July 2023, Friday, July 14, 2023
Tags: #Streets
Street Improvement Projects, Update of all Current Projects
• Although several roads are behind schedule, contractor XIT Paving indicates they will add resources to complete the total Streets Improvement Project, Phase One on time, "The most current project schedule for our 2023 Street Improvements project shows a completion date of December 8th, 2023." City Engineer Gretchen Vazquez. 28 July 2023
• Road Project update: July 21, 2023, Willow Park City Website, 21 July 2023; Details of City of Willow Park post and subsequent Q&A in Willow Park Civics Blogs linked below in Summaries.
• Willow Park Civics Blog > Street Improvement Projects, Phase One
• Willow Park Civics Blog > Street Improvement Projects, Comprehensive
Summaries

• Willow Park Civics Blog > Street Improvement Projects, Crown Road
• from Ranch House Road south to the city limits [concrete]
• Started 28 November 2022
• 75% complete

• Willow Park Civics Blog > Street Improvement Projects, Kings Gate Road
• From Kings Gate Road Bridge to top of hill Castlemont. [concrete]
• Started March 2023.
• 45% complete
• Estimated completion date 31 August 2023

• Willow Park Civics Blog > Street Improvement Projects, Ranch House Road
• From Vista Drive / E.Lake Drive to Crown Road [concrete]
• Started 24 April 2023.
• 45% complete

• Willow Park Civics Blog > Street Improvement Projects, Trinity Drive and Court and Sam Bass Ct [Asphalt Group 1 ]
• Started 24 April 2023
• Driveways 90% complete
• Road reconstruction just started.

• Willow Park Civics Blog > Street Improvement Projects, Old Ford Road, Crested Butte Court, Ridge Haven Court, Pleasant Court [Asphalt Group 2]
• Started 12 July, 2023
• Driveways are 20% complete.
• Road reconstruction will start when driveways are complete.
Not Started
• Sam Bass Drive west from Squaw Creek Road to Ranch House Road, in concrete
• Sam Bass Drive, east from Ranch House Road to El Chico Trail, and tributaries of Fox Hunt Trail, Woodbridge, and Aspenwood Drive, all in asphalt.